Monday, March 31, 2014

IEEE in the Windy City

In just a few short weeks, we'll be in Chicago for IEEE PES T&D Conference and Expo 2014!  If you're planning to join us for some green screen fun and a complimentary souvenir photos, and haven't already done so, you might want to check out and download the official app.  With the app, you can:

  • Easily locate Commonwealth at Booth 8033 (hint, hint!)
  • Populate a schedule of other things you’d like to attend/see
  • Explore a list of exhibitors with information about each and the ability to “favorite” the exhibitor, schedule a visit with them, and/or get directions to their booth
  • View various maps -- exhibits, halls, hotels, etc.
  • View technical program session info, locations, duration and more
  • See a list of speakers, their employers, and when/where they’ll be speaking
  • Access general information about shuttles, the schedule, special events, etc.
  • View and contribute to a photo gallery
  • Follow and contribute to a live Twitter stream using the hashtag #TandD2014
  • Download and view handouts and videos
  • Scan QR codes for more information
  • Figure out where you are in relation to another point
  • View an easy-to-follow ordered map of the exhibitors you choose to bookmark to make the most of your time
  • Discover local Chicago attractions
  • Follow “IEEE PES T&D Conference” on Facebook, and check-in on Facebook when you arrive, for the latest postings there and to contribute to that page
  • Post on LinkedIn regarding the conference 

It's a great resource -- I hope you'll check it out!  See you in Chicago!

-----

Wednesday, August 28, 2013

Teaming up to reduce emissions

We're excited to be part of a collaborative groundbreaking project to provide information which ultimately empowers energy consumers in their daily decision-making about environmental stewardship.  Get the HERO (Home Emissions Read-Out) app HERE.

As Commonwealth's Steve Miller recently put it,“If we are successful, one outcome might be a service which (people) can employ with their appliances. To choose the time of day or place where using their appliance will cause more or less emissions.”

Click HERE to read the full MLive article.

-----

Wednesday, August 14, 2013

Shining the light on outage prevention

 
Today marks the infamous 10th anniversary of the August 14, 2003 blackout of the eastern United States.  The massive outage, or megablackout, determined to be the result of a tree branch in Ohio initially taking out a 345kV line, compounded by cascading failure, affected over 50 million people with an economic fallout estimated at ten billion dollars. 

Over the past decade, a great deal of effort has gone into reducing the chances of a similar widespread outage occurring in the future.  Areas of success include the creation and strengthening of standards associated with the planning and operation of power systems, and the application of new technologies, particularly Phasor Measurement Units (PMU) -- a technology driven by the same GPS technology driving the universal mapping functions in our phones and other applications -- to situational awareness. 

Despite these advances, as more recent incidents demonstrate, more work remains to be done.  Fundamental components, such as transmission lines and transformers that make up the grid, need to be updated and added to meet current needs and the desire to support new generation sources including wind, solar and natural gas fired plants.  When it comes to the potential for cascading outages of the grid, techniques for consistent analyzing these events prior to their occurrence and identifying cost effective remedies are still in their infancy.

Commonwealth Associates is an active participant in planning, identifying, and implementing such solutions and we always welcome opportunities to discuss techniques and collaborate in creating solutions.  For information about our Transmission Grid Analytics - Cascade Analysis (TM) software that helps to prevent future blackouts, click here.  In a nutshell, it provides:
  • A verifiable and complete list of “breaker-to-breaker” contingencies
  • Identification of ALL contingencies that cause violations and a direct or indirect assessment of all double (Category B and C) contingency combinations
  • Analytical methodology to supplement your engineer’s experience and judgment
  • Objective, repeatable, and reasonable classification of contingencies that cause A/R violations into those that will not cause outages beyond a predetermined area and those that cannot be eliminated as potential causes for widespread outages
  • Priority list of trouble facilities that identifies and suggests root causes for contingencies that may initiate widespread outages
  • Independent evaluation of your system suitable for use as compliance documentation that management can include in their "due diligence" reporting
  • Custom solutions

An ounce of prevention is worth a pound of cure.

-----

Wednesday, June 6, 2012

WINDPOWER 2012 Wrap-up



AWEA's WINDPOWER 2012 in Atlanta is quickly coming to a close and our own Linda Gray, Vice President of Business Development, and engineers Gerry Callison and Bob Putnam say it was another great time.  They thoroughly enjoyed getting to talk with folks and hear their concerns and aspirations.  We continue to hear from customers that securing interconnection and transmission rights in MISO can be a difficult and frustrating process. 


The good news is that Commonwealth has vast experience working with both transmission providers and interconnection customers to achieve successful solutions. By employing detailed data not readily available to most and exercising directed and intense attention to the engineering details, including legal and economic, we are pleased to report that Commonwealth has been able to achieve good results for all parties.


Booth visitors were treated to a demonstration of our newest software release, Transmission Grid AnalyticsTM - Mapping.  This great new tool can link a wind resources map to electrical data on the nearest substation and make planning smarter, simpler, and easier.  


Who doesn't want that?
----

Monday, January 30, 2012

[PAPER] MISO MVPs: A Hidden Opportunity for Michigan's Rate Payers and Economy

Editors' Note: Commonwealth's Transmission Mapping Solution was used by Mr. Miller to acquire the information needed to create the map that is the central figure in the presentation.  For more information about   Transmission Mapping for Network Analysis, please click here or view the product list.


Overview
Despite FERC’s ruling to the contrary[1], the conventional wisdom in Michigan is that MISO’s Multi-Value Projects (MVP) scheme for paying for transmission projects is a financial loser for Michigan.

See for example:


Because Michigan is composed of two peninsulas, the thinking is that there isn’t any reason that MVP’s will be built in Michigan.  While this thinking maybe right, let’s examine a concept that might turn this equation on its head.  Before we do, let’s review some of the conditions that create the opportunity for the concept.

Background
For background, here are some key issues:

Geography: While Michigan is composed of peninsulas, we are not Florida.  The Detroit and St. Clair rivers are not the Atlantic Ocean and the Sault River is not the North Sea.  The Straits of Mackinac are negotiable and even Lake Michigan isn’t the Caribbean.

Connection with the regional Independent System Operator MISO: With the shift of members to PJM, Michigan no longer has any significant direct ties with other MISO members.  It might only be a matter of time before Lower Peninsula Michigan entities join the crowd and join PJM without a game changer to reinvigorate the relationship.



MISO Market Area[2]



MISO Reliability Coordination Area[3]

Potential Resources: Michigan has vast amounts of potential renewable energy, mostly wind.  Using the highly successful Ludington Pump Storage plant as an example, Michigan’s lakeshore has the potential for cheap energy storage with proven technology.  If Michigan becomes a hotbed of battery activity, the experience with storage could morph easily into other forms of storage.  Michigan has some natural gas and gas storage and good connections to the natural gas pipeline network making modern natural gas fired generators attractive.  Although some will certainly disagree about the merits of nuclear power, Michigan is seismically stable, free of hurricanes and typhoons, and there has never been a tsunami on Lake Huron. While some may argue that the proximity to its vast fresh water resources is a risk for nuclear power, this risk seems manageable absent the probability of a catastrophic geological event.  Finally, Michigan is in close proximity to Canada and its vast resources of hydro power and, to a lesser extent, natural gas and oil.

Power Supply Challenges: The coal generation in Michigan is old.  Those plants that are not killed by new environmental regulations risk simply dying a natural death from old age.  Michigan’s fate could be worse if this and other aging generation is kept alive by enormous investments in environmental controls and maintaining electric reliability requires Michigan to be at the terminus of massive MVP transmission projects through Illinois, Indiana, and beyond.

Electric Reliability: While efforts are being made to insure bulk power electric reliability, the reality is that these efforts have not yet resulted in infrastructure improvements in the form of transmission improvements that substantially change the structure.  Consequently, the next Northeast blackout is going to look pretty much like the last two with system separation occurring somewhere in Michigan, east in Ontario, or east along lines through Ohio, Pennsylvania, and western New York.  Provided AEP’s network of 765 kV lines does not become overloaded with power flowing from “PJM West” to the original parts of PJM and NYISO, the cascading blackout will stop north of this 765 kV back bone.

Concept
With these facts held in mind, our concept is that Michigan should be a Mecca for major transmission projects with the MVP designation.  Specifically, these projects would be major transmission lines crossing the Upper Peninsula and major transmission lines, similar to the 765 kV projects that ITC once proposed, built between Chicago and Detroit.  


The proposed MVP in the Lower Peninsula would originate at the 765 kV Dumont substation or at the Cook Power plant that is served by a radial extension of the 765 kV network.  Following mostly existing right-of-ways, it would go north to Kenowa (or Vegennes) and turn east to pass Thetford and end at Scott (Lambton).  A segment south from Thetford to Marysville or South Canton might also be added.

On the west, extensions to Collins or Plano could be added to meet up with new transmission supporting renewable generation in the Northern Plains.  On the east, extension to Longwood would add a tie to the Canadian 500 kV system.

The proposed MVP in the Upper Peninsula would consist of segments from western Wisconsin (or Minnesota) to Sault Saint Marie, from Arnold to Saint Ignace, from Saint Ignace to Sault Saint Marie, and from Saint Ignace and the Straights to Livingston.  Construction of this could be at 345 kV, 500 kV, 765 kV, direct current.  The project in the east could be extended to the Hamner substation to tie into the Canadian 500 kV.  The key idea is to build massive transmission to take renewable energy generation from Minnesota and the Dakotas and ship it to the Midwest and beyond.  The path from these regions and the Midwest and New York and beyond is shorter than the path around the south end of Lake Michigan and it avoids the heavy congestion around the south end of Lake Michigan.

Perhaps the most radical feature of this connection is a new, international connection at the Sault, where no substantial connection currently exists.  Controlling the flows in a precisely regulated way may be desirable and necessary at the connection points to Canada. To do so requires modern back-to-back converters like the one currently being installed in New Jersey to service a new connection to New York.

Here are some rough estimates of segment lengths that are probably biased on the low side because they may not include enough length to account for routing compromises.

Segment
Length (miles)
Stone Lake – Hanmer
543
9 Mile – St Ignace
40
Gardner Park – St. Ignace
274
St. Ignace – Livingston
58
Dumont – Thetford
223
Thetford - Lambton
90
Lambton –Longwood
45
Thetford – South Canton
257
Total
1,530

Concept Benefits
While no thorough study of all the elements of this concept have been made, aside from directing more MVPs to Michigan, it has some immediate, obvious potential benefits, in that it:

  • Provides a transmission backbone to import and export power into and through Michigan. Ideally this would help lead to a self-sufficient Michigan and perhaps increase the likelihood that Michigan might become a net generation exporter, both to the west to Chicago and to the east to NYISO and PJM.  Ties to Canada would allow better resource management with opportunities for optimizing the use of Canadian hydro versus renewable energy resources in Michigan.  The concept provides an alternative path and exploits existing transmission resource for renewable electric generation originating from the Upper Midwest to New York and PJM.  This concept should be advantageous compared to alternatives because it avoids both transmission congestion and corridor congestion south of Lake Michigan.
  • Increases the regional system reliability. The plan addresses local reliability problems associated with importing power into southwest Michigan and local problems in the Upper Peninsula.  It also has the potential for addressing super regional problems such as the loop flows around Lake Erie and underlying problems that would reduce the probability of another “northeast” blackout.
  • The concept restores physical ties and strengthens virtual ties to MISO.  This should have a variety of advantages, including making operations easier and reducing or eliminating difficulties associated with constructing a reasonable market, including impacts on LMP calculations.  If Michigan eventually goes to PJM, the infrastructure will retain or have enhanced value.


Michigan Support for the Concept
Provided this concept has merit, other than promoting the idea so that it is studied and understood, the concept of building MVP transmission in Michigan should stand on its own when compared to other methods of addressing the regions transmission needs.  That said, here some thoughts on how Michigan can enhance the chances of obtaining MISO MVPs.

  • Create a regulatory climate that removes barriers to long linear projects while protecting the legitimate interests of stakeholders.  Uniform statewide rules with respect to acquiring right-of-way are important.  The State could review its land holdings to see if any are appropriate for this activity.  Michigan already has a leg up, because its transmission is owned by strongly-favored independent transmission owners.  While both are unique, either is, or would be, a great proponent of these projects.
  • Exercise Michigan’s long standing skills as a border state and its knowledge of international projects with Canada.  Canadian “buy in” would go a long way to add value to these projects.  This is not trivial, because the relationship between MISO and the Ontario Independent System operator is not robust, at least not in the planning activity.
  • Generation drives transmission, so Michigan should make it as easy as reasonably possible to build wind, natural gas, and pumped storage generation.  Michigan is a net importer of electric energy and fuel to produce the electric energy that is generated in Michigan.  Although it is not an issue for wind-generated energy, water is often a key component of thermal generation projects.  We should be sure that Michigan’s advantage is not negated by national rules that are appropriate for water usage from sources such as the Colorado River and regions like the Southwest, but irrelevant to the water conditions in Michigan.  Provided the generation is economically competitive in Michigan and for export, Michigan’s economy would be greatly enhanced by being self-sufficient, or even a net provider of electric power.
  • Continue to look for opportunities to create new storage technologies, particularly those associated with the automotive industry.  Michigan needs to be smart and shouldn’t chase technology for technology’s sake, but if the economic case can be made, the link should be exploited. For example, because battery packs have useful life after they are no longer useful in an automotive application, their remaining capabilities might be exploited in fixed plants providing storage for the grid.  This could result in a valuable link in the economic and environmental life cycle of automotive battery packs.
In conclusion, MISO MVPs may be bad policy for Michigan, but we have outlined a concept that can and should be explored that would result in MVP dollars being spent in Michigan on alternatives that are potentially superior to those proposed or that are in the planning stages.

©2012 Commonwealth Associates, Inc. and Stephen S. Miller, P.E.

Thursday, January 26, 2012

MISO MVPs and Michigan: Bad policy or hidden opportunity?




In an October 21st posting, we addressed the Federal Energy Regulatory Commission's (FERC) ruling on the Midwest Independent Transmission System Operator, Inc.'s (MISO) multi-value projects (MVPs) cost allocation scheme and the strong response to it in Michigan, a state in which it is being questioned whether or not the costs will actually be in line with the benefits received (see http://commonwealthassociates.blogspot.com/2011/10/federal-energy-regulatory-commission.html).

Stephen S. Miller, P.E.
Commonwealth's Stephen S. Miller, P.E., Section Manager for TRANSMISSION 2000®, will be offering an interesting take on the situation tomorrow, Friday, January 27th, as one of the featured speakers at the Michigan Forum on Economic Regulatory Policy put on by Michigan State University's Institute of Public Utilities at the Kellogg Center in East Lansing.  He will be taking a look at Michigan's unique geography, the connection with the regional Independent System Operator, potential resources, power supply challenges, electric reliability, international relations, and new technologies, particularly those associated with the automotive industry.

Miller has more than 33 years of experience in the analysis and planning of electric utility systems and the design and development of associated software programs, particularly the TRANSMISSION 2000® series of programs -- including Power Flow, Short Circuit, and Transient Stability -- designed to improve the analysis and planning of utility transmission systems.


A copy of his presentation will be posted here.

-----

Friday, January 6, 2012

Coming to Life Beneath the Hudson

                       Photo by Fred R. Conrad/The New York Times

Like proud parents watching their child walk for a diploma, one of Commonwealth's goals for our conceptual plans and project evaluations is to see them written in steel and concrete.  However, for a variety of reasons, planning studies frequently result in long-forgotten reports buried on a shelf or an electronic drive somewhere.  We are proud to provide our clients with the experience, talent, and unique combination of resources that turn concepts into projects -- projects like the one, years in the planning, now coming to life beneath the Hudson River between Midtown Manhattan and New Jersey in New York Harbor.

In 2006, Commonwealth assisted the New York Power Authority (NYPA) with evaluating power supply options for New York City.  Shortly after providing advice in the form of study conclusions and work papers, NYPA selected the project we recommended.  This New York Times article highlights the progress toward implementation of that project.

http://www.nytimes.com/2011/12/27/nyregion/crew-lays-power-cable-beneath-the-hudson.html?_r=1

http://www.projectfinancemagazine.com/Article/2413302/Sectors-Power/NYPA-picks-New-York-City-suppliers.html

-----

Wednesday, November 2, 2011

What's in our energy future?


What is the right mix of energy for the future of America? 

The globe? 

You personally? 

Population has just hit the 7 billion mark.  What does that mean in terms of energy demand?  This article asks the question, "When should we pursue energy transition?"

What are your thoughts?

http://www.smartplanet.com/blog/energy-futurist/when-should-we-pursue-energy-transition/159

-------

Friday, October 21, 2011

The irk with FERC


The Federal Energy Regulatory Commission (FERC) met yesterday and reaffirmed their approval of MISO's transmission planning process, potentially sparking further litigation. In support of yesterday's actions, FERC issued this press release.

MISO territory map
FERC's Order 1000 speaks to the issue of whether states can be forced to coordinate on transmission planning and meeting cost obligations for new electricity transmission capacity. It holds that states can be compelled -- which, not unexpectedly, has raised some dander.

That is particularly the case in states such as Michigan, where it is believed that the cost of the tariff would not fairly reflect the limited benefits Michigan would receive, given the state's unique geography. The gold-colored areas on the map above shows MISO's territory.

Steven Transeth
Steven Transeth, consultant for MISO Northeast Customer Coalition and former Michigan Public Service Commissioner wrote this article, published earlier this year in the Wall Street Journal, setting out Michigan's case.

In a telephone interview Thursday, Transeth commented that the meeting offered little to improve the situation of Michigan, which he calls the "worst case scenario" among states.  "The Commission's actions demonstrated that, regardless of the rhetoric, FERC intends to push a socialized approach in which rates are not commensurate, costs are not ‘just and reasonable,’ and authority is improperly delegated to a regional group with [differing] loyalties,” said Transeth.

An archived webcast of yesterday's meeting can be found here.

---

Friday, August 19, 2011

Don't be in the dark about power outages

Check out this article by Stephen S. Miller, Senior Member of IEEE, entitled "Extending Traditional Planning Methods to Evaluate the Potential for Cascading Failures in Electric Power Grids."

http://www.cai-engr.com/content/corp/IEEEPanelCA.pdf


Stephen S. Miller, P.E.
Mr. Miller, Section Manager for Commonwealth Associates, Inc.'s TRANSMISSION 2000 (R) software, is active on the IEEE PES CAMS Task Force on Understanding, Prediction, Mitigation, and Restoration of Cascading Failures.  He holds BSEE, MSEE, and EE degrees from the University of Michigan.

Wednesday, August 10, 2011

Welcome!

Thanks for stopping by! 

You might have heard people say we offer great services (which we appreciate!), but we also have a great story you may not have already heard.  It speaks to who we are as a company and what we can do for you, whether you benefit from our work as an end user, seek employment with us, or are contemplating doing business with us -- which we strongly believe you should!

You see, Commonwealth was established in 1988, following the closing of another engineering firm's Jackson, Michigan, office.  The founders had worked closely together on domestic and foreign electric transmission and distribution projects for many years out of the Jackson office.  Rather than leave Jackson, Commonwealth's founders left and company and took action to incorporate under a name that was -- and remains -- well known and respected in the electric power industry.  The group devoted itself to structuring a new employee-owned company with the intent of upholding the previous Commonwealth Associates, Inc.'s reputation for providing high-quality engineering and consulting services.  Other talented individuals, many of whom had worked previously with the founders, were brought in to lend their expertise.  The new company flourished, and Commonwealth opened another office in the state of Washington in 1992 to serve clients in the western United States.  Another principal office was opened near Atlanta, Georgia, in 2008.

Today, Commonwealth's staff of approximately 200 professional and technical employees represents one of the most skilled, experienced technical resources available to analyze, plan, design, and construct electric power delivery projects.  In addition to licensed engineers and engineering specialists, we have experts in environmental sciences, licensing, Geographical Information Systems (GIS), surveying, right-of-way acquisition, and construction management, many of whom have more than 20 years of experience in their fields.  Many of our professional engineers are active members of the Institute of Electrical and Electronics Engineers, American Society of Civil Engineers, Edison Electrical Institute, and National Society of Professional Engineers, which allows interaction with our peers and gives us access to problem-solving resources directed to the T&D industry.

Commonwealth's methods and tools have evolved over the years to incorporate emerging technologies and meet new challenges, but our devotion to engineering excellence has remained the same.

As we like to say, "At Commonwealth, you can Connect with Confidence"!


_____________

Learn more about us at: www.cai-engr.com.

Follow us on Twitter: twitter.com/caiengr_dot_com (We tweet job openings!)

To serve clients throughout the United States efficiently, Commonwealth has offices in the following locations:

Jackson, MI
Mount Vernon, WA
Kennesaw, GA
Roanoke, VA
Columbus, OH
Dayton, OH